Year: 2021
Country: Ukraine
Industry: Production of ceramics and building materials
Task:
• repair of the lining of the heat exchanger of the afterburner on production lines No. 1 and No. 2;
• thermal insulation of air ducts and heat exchanger of production line No. 1 and sections afterburner unit's heat exchanger casing sections on production line No. 1.
Implementation:
• production and installation of anchors and bandages for fixing thermal insulation materials;
• installation of high-temperature thermal insulation materials;
• installation of LYTX ceramic fiber mats;
• manufacture, supply and installation of LYTX-1140M ceramic fiber modules of various standard sizes.
Result:
• work was performed in accordance with contractual obligations, in two shifts and within a short time frame (10 and 14 calendar days for each production line, respectively);
• a positive customer's feedback is received.